ACE

Construction update provided from Atlantic City Electric, contingent on weather.

In regards to the HDD, 95th and Sunset will remain closed for safety reasons until the HDD process has been completed.

There is one more sheet pile that needs to be installed which is tentatively scheduled for Wednesday, March 23rd.

Work on the HDD process is tentatively scheduled March 30th and 31st.

The manhole will be delivered on March 28th and set on March 29th on 95th Street.

In regards to our open cut for the underground ACE is currently in front of 357 95th St. heading west.

The Matrix crew is working this Saturday and starting next week working 5 days a week from 7:00am to 6:00pm in order to stay on schedule.