Progress Update and Anticipated Schedule

Atlantic City Electric has completed splicing in the 95th Street manhole and has begun terminating the west end riser. The cable installation crew has installed racking and grounding in the Hallman Road Manhole on the Middle Township side of the project.

 

Thursday, June 23rd, 2016

Terminating on the Middle Township side riser and Hallman Road manhole clamping and grounding installation will continue.

 

Friday, June 24th & Saturday, June 25th

Atlantic City Electric Crews will be working in Stone Harbor to complete the fiber cable pull and terminate to create a communication path to Peermont Substation.

 

Preliminary Test to energize the service line is scheduled for June 30th, 2016