Phase III ~ Outfall Elimination Project ~ Status Report

All utilities, concrete curb & gutter and base course has been completed on  82nd St. and Second Ave.   The hot asphalt surface course will be installed prior to the “summer shutdown” (Memorial Day).

Contractor shall have installed all sanitary sewers, storm drains, water mains, curbs and gutter on First Ave. from the Park (81st St) to 85th Street and the base pavement up to 83rd St. by EASTER weekend.

The Contractor may continue to work along First Ave., block by block, if he believes he will be able to install the base pavement prior to the summer shutdown.

Additional Updates will be posted as they become available.

 