****NJ – TOWNSENDS INLET – BEACH NOURISHMENT – AVALON TO STONE HARBOR****
Great Lakes Dredge and Dock will begin beach nourishment from Townsends Inlet to Cape May Inlet. Beach fill will start from Avalon 9th Street to 32nd
Street Avalon, NJ and Stone Harbor 91th Street to 122th Street, Stone Harbor, NJ. The Cutter Suction Dredge (CSD) Texas will dredge material from
the Townsends Inlet Borrow Area, located approximately 5,000 feet offshore, northeast of the project location, west of the Townsends Inlet. The material
will pump through one subline extending from the borrow
area to the placement beach. GLDD has secured two waterside staging areas on the Cape May Inlet where rafted pipeline and equipment will be stored
when not in use. The survey vessel and crew transfer vessel (CTV) Saginaw River will traverse between the work areas and Avalon Marina throughout
the duration of the project. All vessels will monitor VHF – FM 16 & 13. Dredging will be conducted 24 hours a day, 7 days a week and is expected to be
completed June 30, 2023.
Chart 12318 LNM 04/23

The LNM (Local Notice to Mariners) can be found online at: https://www.navcen.uscg.gov
Local Notice to Mariners, District 5, January, 04/23 Weekly Edition