July 9, 2023
Daily Beach Nourishment Update and Beach Closures:
- Currently Beaches are Closed from 121st to 122nd streets for beach nourishment operations.
- Protected Beach closed at 122nd Street
- Most advanced basket discharge station: 121st Street
- The Dredge, Texas, and Booster are on site waiting for repairs to the air valve on the float hose, repairs are being done in CM Inlet. GLDD estimates the repairs and tow back to TI with reconnection to the dredge to be mid-afternoon early evening.
- Subline landing in Stone Harbor at 91st Street
- Dredge, Texas, pumped approximately 27,234CY onto beach on 7/8/23 from 0000 hours to 2400 hours; total placed on beach to date (7/8/23, 2400 hours): 568,373 CY, 77.55 % complete (per GLDD).
- Dredge Texas pumped approximately 0 CY onto beach on 7/9/23 from 0000 hours to 0700 hours.