July 10, 2023

Daily Beach Nourishment Update, July 10, 2023

  • Currently beaches from 121st Street through 123rd Street are closed due to beach nourishment operations.
  • The protected beach at 122nd Street is closed (no lifeguards)
  • Most advanced basket discharge station: 121st Street
  • The Dredge, Texas, is being towed from Townsends Inlet into Cape May Inlet for repairs.
  • The Booster is onsite waiting for repairs to the dredge, Texas, to be completed in Cape May Inlet. GLDD did not give an estimate for when the repairs and tow back to the borrow area is expected
  • Subline landing in Stone Harbor at 91st Street
  • Dredge Texas pumped approximately 10,598 CY onto beach on 7/9/23 from 0000 hours to 2400 hours; total placed on beach to date (7/9/23, 2400 hours): 578,971 CY, 79.00 % complete (per GLDD).
  • Dredge Texas pumped approximately 1,141  CY onto beach on 7/10/23 from 0000 hours to 0700 hours