July 7, 2023

The beach-fill has been completed south to the 115th street taper, Great Lakes  Dredge and Dock finished piping through the 119th street taper and is now filling south of 119th Street. Each street end north of the current work area has a ramp over the beach pipe for public use.

– Currently, beaches from 119th to 122nd Streets are closed for beach nourishment operations.

– Expect intermittent closures of the 123rd Street parking lot for mobilization/storage of equipment and supplies

– Most advanced basket discharge station: 119th Street

– The Dredge, Texas and Booster are on site and working

– Subline landing in Stone Harbor at 91st Street

– Dredge, Texas, pumped approximately 11,064 CY onto beach on 7/6/23 from 0000 hours to 2400 hours; total placed on beach to date (7/6/23, 2400 hours): 510,020 CY, 69.59% complete (per GLDD).

– Dredge, Texas, pumped approximately 7,418 CY onto beach on 7/7/23 from 0000 hours to 0700 hours.