July 18, 2023

BEACH CLOSURE & BEACH NOURISHMENT UPDATE

–  Currently the beach and parking lot are closed at 123rd Street for demobilization operations.

– The Dredge, Texas, and Booster are currently off site at the Cape May Inlet.

– Subline landing in Stone Harbor at 91st Street

– Dredge Texas pumped approximately 16,665 CY onto beach on 7/17/23 from 0000 hours to 2400 hours; total placed on beach to date (7/17/23, 2400 hours): 727,755 CY, 100% complete (per GLDD).

– Beachfill operation completed as of yesterday, 7/17/23.

– Disassembling of shore pipes from south to north in progress and consolidating at 123rd St beach.

– Demobilization of equipment from the beach to commence on 7/20/23.