Beach Replenishment News Archives

Important Information – July 4th Fireworks (2023)

July 3, 2023

A cherished tradition continues as Stone Harbor gears up to celebrate Independence Day with a fantastic fireworks display on the evening of July 4th!

Set from a barge off the 95th Street beach, the fireworks will commence at dusk, approximately 9:15 pm. It’s an event not to be missed! However, there are a few important things to note to ensure you have a memorable and hassle-free experience.

Prime Fireworks Viewing: To witness the fireworks, find a cozy spot along Stone Harbor’s beautiful beachfront. However, please be aware that due to the ongoing beach replenishment project, some beaches south of 110th Street may not be accessible.  This project operates 24/7, but rest assured the end result will be beautiful and enhanced beaches, but it means that 4-6 blocks of beachfront will be temporarily unavailable on July 4th. Currently beaches are closed from 110th St. – 111th St., but it is anticipated that beaches will be closed through 114th Street as the day progresses. Updates will be posted as the information is received.

Navigating Beach Access: For visitors heading to the beach, it’s essential to be mindful of the large subline piping installed along our beaches south of 91st Street. To ensure your safety, designated crossovers have been constructed at each beach entrance. These crossovers provide a secure way to traverse the pipe and access the beach. We apologize for any inconvenience caused by this necessary operation, but the future benefits of an enhanced beach will be well worth it.

Stone Harbor’s Independence Day celebrations are meant to be enjoyed by both local residents and visitors. With the much-anticipated fireworks display and ongoing beach replenishment project, it’s important to plan your visit accordingly. Take note of the accessible beach areas and utilize the designated crossovers for a safe beach experience. Enjoy the holiday and celebrate the spirit of independence in Stone Harbor!

Important Information – July 4th Fireworks (2023)2023-07-31T09:40:56-04:00

Beach Closures, July 3, 2023: 110th St. – 111th St; Closures Could Extend to 114th St. Later Today

July 3, 2023

DAILY BEACH CLOSURE UPDATE, JULY 3, 2023:
– Beaches and crossovers are closed from 110th St. – 111th St. for beach nourishment operations.
– Protected beach at 110th Street is closed – No lifeguards on duty.
– Please note that beach closures could extend to 114th St. later today if subline repairs are completed.
– Intermittent closures of the123rd Street parking lot for mobilization/storage of equipment and supplies.
– Most advanced basket discharge station: 111th St.
– The Dredge, Texas and Booster are on site NOT working…waiting for sea conditions to lay down to allow for safe repairs to the damaged subline on the discharge side of the booster-pump.
– Dredging will resume when issues have been rectified; possibly today.

Beach Closures, July 3, 2023: 110th St. – 111th St; Closures Could Extend to 114th St. Later Today2023-07-31T09:40:32-04:00

BEACH CLOSURE & BEACH FILL UPDATE AS OF 2:00 PM, JULY 2, 2023:

July 2, 2023, 2:00 p.m.

BEACH CLOSURE & BEACH FILL UPDATE AS OF 2:00 PM, JULY 2, 2023:

Due to rough seas the subline repairs have been pushed to tomorrow.

GLDD has consolidated their beach fill construction site and has opened 700’ of beach to the public for today ONLY.

Current street crossover closures by GLDD are:
– 110th St. & 111th St. ADA access.
BEACH CLOSURE & BEACH FILL UPDATE AS OF 2:00 PM, JULY 2, 2023:2023-07-31T09:40:18-04:00

DAILY UPDATE: JULY 2, 2023 BEACH CLOSURES & BEACH NOURISHMENT

July 2, 2023

DAILY UPDATE: JULY 2, 2023 BEACH CLOSURES & BEACH NOURISHMENT
– Beaches & Crossovers are closed from 110th to 113th Streets for beach nourishment operations.
– Expect intermittent closures of the 123rd Street parking lot for mobilization/storage of equipment and supplies.
– Most advanced basket discharge station: 111th Street
– The Dredge, Texas, and Booster are on site.
– Subline landing in Stone Harbor at 91st Street
– Dredge, Texas, has pumped approximately 483,597 CY of sand to date (per GLDD).
– Dredge Texas is currently down for subline issues. The Booster pump generator issue has been repaired. Dredging will resume when issues have been rectified. Projected to be sometime today.
DAILY UPDATE: JULY 2, 2023 BEACH CLOSURES & BEACH NOURISHMENT2023-07-31T09:40:07-04:00

July 1, 2023 Beach Closures and Beach Nourishment Update

July 1, 2023

JULY 1st BEACH CLOSURES & BEACH NOURISHMENT UPDATE
– Beaches are closed from 110th to 113th Streets for beach nourishment operations.
– Protected beaches are closed at  110th Street and 112th Street
– 123rd Street parking lot for mobilization/storage of equipment and supplies (intermittent closures).
– Most advanced basket discharge station: 111th Street
– The Dredge, Texas, and Booster are on site.
– Subline landing in Stone Harbor at 91st Street.
– Dredge Texas is currently down for mechanical issues on the Booster. A technician is onsite and working to repair the booster pump generator. Dredging will resume when issue has been rectified.
July 1, 2023 Beach Closures and Beach Nourishment Update2023-07-31T09:39:56-04:00

Beach Closures and Beach Nourishment Update for June 30, 2023

June 30, 2023

Beach Closures and Beach Nourishment Update for June 30, 2023

Current street crossover closures by Great Lakes Dredge & Dock, Co. (GLDD):

  • 110th to 113th streets for beach nourishment operations.
  • 123rd Street parking lot for mobilization/storage of equipment and supplies (intermittent closures).

Protected Beaches are closed at:

  • 90th St. – subline landing area
  • 110th St. and 112th St. for beach nourishment activity

Most advanced basket discharge station: 111th Street

The Dredge, Texas, is currently down for mechanical issues on the Booster.  Technician is arriving at 10:00 am to repair the booster pump generator according to GLDD.  Dredging will resume when issue has been rectified.

Beach Closures and Beach Nourishment Update for June 30, 20232023-07-31T09:39:46-04:00

Beach Closures for June 29, 2023 Due to Beach Nourishment Project

June 29, 2023

TODAY’S BEACH CLOSURES (June 29, 2023) DUE TO BEACH NOURISHMENT PROJECT:

– Beaches are closed at 90th Street and from 109th to 112th Streets for beach nourishment operations.

– Expect intermittent closures of the 123rd Street parking lot for mobilization/storage of equipment and supplies

– Most advanced basket discharge station: 111th Street

– The Dredge, Texas, and Booster are on site and working.

Beach Closures for June 29, 2023 Due to Beach Nourishment Project2023-07-31T09:39:29-04:00

Beach Closures for June 28, 2023 Due to Beach Nourishment Operations

June 28, 2023

TODAY’S BEACH CLOSURE UPDATE (June 28, 2023) DUE TO BEACH NOURISHMENT PROJECT:

– Beaches are closed from 109th to 112th streets while beach nourishment activity is in progress.

– Expect intermittent closures of the 123rd Street parking lot for mobilization/storage of equipment and supplies

– Most advanced basket discharge station: 109th/110th Streets

– Dredge is idle at this time….expectation is to begin dredging this afternoon. The dredge, Texas, and booster are on site.
Beach Closures for June 28, 2023 Due to Beach Nourishment Operations2023-07-31T09:39:16-04:00

Beach Closures and Beach Nourishment Update for June 27, 2023

June 27, 2023

– Beaches are closed from 109th St. to 112th St. for beach nourishment operations.
– Expect intermittent closures of the 123rd Street parking lot for mobilization/storage of equipment and supplies.
– Most advanced basket discharge station: 109th/110th Streets
– The Dredge, Texas, is idle at this time. Both the dredge and booster pump are on site waiting for high tide to move anchors on the Texas. Rough sea conditions prohibited anchor movement last evening.

 